Required documents for Consent to Operate (CTO)
Application for Consent to operate under Water Act, 1974/ Air Act, 1981 for Red/Orange Category - Fresh Case
- Compliance report of NOC / Consent Conditions in annotated form
- Completion certificate of ETP/APCD alongwith Dimensional Drawing
- Plan showing the location of ETP/APCD and all outlets and various channels/pipes/sewers with requisite colours as detailed below:-
- Fresh Water.:.... Blue Colour.
- Effluent Channel- Red Colour.
- Recirculation Water Channel - Green Colour.
- Storm Water - Orange Colour.
- Domestic Sewer - Dotted Black ink.
- CA's certificate regarding un-depreciated value of the fixed assets of the industry at the end of last financial year.
NOTE : In case the industry is already established / operational, following additional documents are also required to be uploaded.
i. Site Plan/Location Plan of the industry.
ii. Proof of date commissioning of the Industry ( Registration of the industry/ Electricity bill /Sales Tax no )
iii. Manufacturing process details along with the process flow chart.
iv. Latest granted CTE/CTO, if obtained offline, then copy of CTE/CTO granted to be uploaded.
v. Analysis report of treated waste effluent / emission from Board / Approved Lab.
vi. Documents regarding designation of area/compliance of specific guidelines (Any one of the following:
a) Allotment letter of the Allotting Authority, if the site of the project is located in the designated Industrial Area/ Industrial Estate/ Focal Point.
Or
b) Certificate from the Designated Authority to the effect that the site of the project / industry is located in the designated Industrial zone/ area of the notified/ draft Master Plan in which the establishment of such industry/ project is permissible. The undertaking shall clearly indicate the revenue entries I.e. Hadbast Number, khewat /khatauni number and Khasra numbers.
Or
c) Certificate of Revenue Authorities (DC/ADC/SDM) indicating the distance of site of industry from the MC Iimits/Phirni / Lallakir of the nearest village, in case, the industry is to be established at a site other than the site in the industrial area / industrial estate /industrial zone of the draft master plan / industrial zone of the notified master plan.
Or
d) For industry specific guidelines, certificates/ documents as mentioned in the said guidelines (In case of Rice Sheller/Saila Plant/Stone Crusher/Brick Kiln/Hot Mix plant/Cement Grinding units etc.)
Note: 1. In case the NOC was not granted online, you requested to submit a copy NOC granted, copy of Project Report and Feasibility Report submitted at the time of obtaining NOC.
2. Application shall be accompanied by CTO fee as per the un-depreciated fixed assets of industry as per the policy dt. 04/2013 of the Board available on the website of the Board at www.ppcb.gov.in
Application for Consent to operate under Water Act, 1974/ Air Act, 1981 for Green Category - Fresh Case
1. Compliance report of NOC / Consent Conditions in annotated form.
2. CA's certificate regarding un-depreciated value of the fixed assets of the industry at the end of last financial year.
NOTE : In case the industry is already established / operational, following additional documents are also required to be uploaded.
i) Site Plan/Location Plan of the industry.
ii) Proof of date commissioning of the Industry
iii) Manufacturing process details along with the process flow chart.
iv) Latest granted CTE/CTO, if obtained offline, then copy of CTE/CTO granted to be uploaded.
v) Documents regarding designation of area/compliance of specific guidelines (Any one of the following:
a) Allotment letter of the Allotting Authority, if the site of the project is located in the designated Industrial Area/ Industrial Estate/ Focal Point.
Or
b) Certificate from the Designated Authority to the effect that the site of the project / industry is located in the designated Industrial zone/ area of the notified/ draft Master Plan in which the establishment of such industry/ project is permissible. The undertaking shall clearly indicate the revenue entries I.e. Hadbast Number, khewat /khatauni number and Khasra numbers.
Or
c) Certificate of Revenue Authorities (DC/ADC/SDM) indicating the distance of site of industry from the MC Iimits/Phirni / Lallakir of the
nearest village, in case, the industry is to be established at a site other than the site in the industrial area / industrial estate /industrial zone of the draft master plan / industrial zone of the notified master plan.
Note: 1. In case the NOC was not granted online, you requested to submit a copy NOC granted, copy of Project Report and Feasibility Report submitted at the time of obtaining NOC.
2. Application shall be accompanied by CTO fee as per the un-depreciated fixed assets of industry as per the policy dt. 04/2013 of the Board available on the website of the Board at www.ppcb.gov.in