Fresh Consent (CTO)

Required documents for Consent to Operate (CTO)


Application for Consent to operate under Water Act, 1974/ Air Act, 1981 for Red/Orange Category - Fresh Case 

1.          Compliance report of NOC / Consent Conditions in annotated form

2.          Completion certificate of ETP/APCD alongwith Dimensional Drawing

3.          Plan showing the location of ETP/APCD and all outlets and various channels/pipes/sewers with requisite colours as detailed below:

a)               Fresh Water.:.... Blue Colour

b)              Effluent Channel- Red Colour.

c)               Recirculation Water Channel - Green Colour.

d)              Storm Water - Orange Colour.

e)               Domestic Sewer - Dotted Black ink.

4.        CA's certificate regarding un-depreciated value of the fixed assets of the industry at the end of last financial year.

NOTE : In case the industry is already established / operational, following additional documents are also required  to be uploaded.

    i.       Site Plan/Location Plan of the industry.

   ii.       Proof of date commissioning of the Industry ( Registration of the industry/ Electricity bill /Sales Tax no )

  iii.      Manufacturing process details along with the process flow chart.

  iv.      Latest granted CTE/CTO, if obtained offline, then copy of CTE/CTO granted to be uploaded.

   v.       Analysis report of treated waste effluent / emission from Board / Approved Lab.

 vi.      Documents regarding designation of area/compliance of specific guidelines (Any one of the following:

a)         Allotment letter of the Allotting Authority, if the site of the project is located in the designated Industrial Area/  Industrial Estate/ Focal Point.

Or

 b)      Certificate from the Designated Authority to the effect that the site of the project / industry is located in the designated Industrial zone/ area of the notified/ draft Master Plan in which the establishment of such industry/ project is permissible. The undertaking shall clearly indicate the revenue entries I.e. Hadbast Number, khewat /khatauni number and Khasra numbers.

Or

 c)    Certificate of Revenue Authorities (DC/ADC/SDM) indicating the distance of site of industry from the MC Iimits/Phirni / Lallakir of the nearest village, in case, the industry is to be established at a site other than the site in the industrial area / industrial estate /industrial zone of the draft master plan / industrial zone of the notified master plan.          

Or

d)       For industry specific guidelines, certificates/ documents as mentioned in the said guidelines (In case of Rice Sheller/Saila Plant/Stone Crusher/Brick Kiln/Hot Mix plant/Cement Grinding units etc.)

Note:  1. In case the NOC was not granted online, you requested to submit a copy NOC granted, copy of Project Report and Feasibility Report submitted at the time of obtaining NOC.

             2.  Application shall be accompanied by CTO fee  as per the un-depreciated fixed assets of industry as per the policy dt. 04/2013 of the Board available on the website of the Board at www.ppcb.gov.in  

     

Application for Consent to operate under Water Act, 1974/ Air Act, 1981 for Green  Category - Fresh Case

 1.            Compliance report of NOC / Consent Conditions in annotated form.

  2.            CA's certificate regarding un-depreciated value of the fixed assets of the industry at the end of last financial year.

NOTE : In case the industry is already established / operational, following additional documents are also required  to be uploaded.

i)       Site Plan/Location Plan of the industry.

ii)       Proof of date commissioning of the Industry

iii)      Manufacturing process details along with the process flow chart.

iv)     Latest granted CTE/CTO, if obtained offline, then copy of CTE/CTO granted to be uploaded.

v)      Documents regarding designation of area/compliance of specific guidelines (Any one of the following:

a)                Allotment letter of the Allotting Authority, if the site of the project is located in the designated Industrial Area/  Industrial Estate/ Focal Point.

Or

 b)     Certificate from the Designated Authority to the effect that the site of the project / industry is located in the designated Industrial zone/ area of the notified/ draft Master Plan in which the establishment of such industry/ project is permissible. The undertaking shall clearly indicate the revenue entries I.e. Hadbast Number, khewat /khatauni number and Khasra numbers.

Or

 c)      Certificate of Revenue Authorities (DC/ADC/SDM) indicating the distance of site of industry from the MC Iimits/Phirni / Lallakir of the

 

        nearest village, in case, the industry is to be established at a site other than the site in the industrial area / industrial estate /industrial zone of the draft master plan / industrial zone of the notified master plan.   

Note:  1. In case the NOC was not granted online, you requested to submit a copy NOC granted, copy of Project Report and Feasibility Report submitted at the time of obtaining NOC.

             2.  Application shall be accompanied by CTO fee  as per the un-depreciated fixed assets of industry as per the policy dt. 04/2013 of the Board available on the website of the Board at www.ppcb.gov.in      

 

    Office Order - regarding mandatory documents required for 'Consent to Establish' (CTE)/'Consent to Operate for fresh/renewal cases  (Size: 4 MB, Format: PDF, Language: English)